Home: Community full menu: Education and Learning full menu: Building schools for the future

Timeline for next steps

Gillian Donohoe - April 2009
school.organisation@kirklees.gov.uk

Subject to decisions made by Cabinet, the indicative timeline for the next stages of the statutory processes are set out below:

Indicative timeline for statutory processes
Date Further Consultation and Statutory Proposals and notices
20 April to 5 June 2009 Further consultation - 7 weeks (including 1 week school holiday) consultation on revised proposals
**19 June to 31 July 2009 Statutory proposals and notices
Publication of statutory proposals and notices for Castle Hall School and The Mirfield Free Grammar and start of 6 week representation period ** Note below
14 July 2009 Report outcomes of further consultation
Report outcomes of the consultation to Cabinet and decisions on next steps for revised proposals
21 August 2009 Publish 1st Competition Notice for new school(s) and submission of proposals – this is an invitation to interested parties to bring forward proposals for setting up the new school(s) (4 months allowed)
4 September to 16 October 2009 Publication of statutory proposals and notices for Whitcliffe Mount – SBEC (VC) *, Gomersal CE (C) Middle School*, West End Middle School* and Whitechapel Middle School* and 6 week representation period.
*subject to cabinet approval
8 September 2009 Cabinet meet and decide proposals for Castle Hall School and The Mirfield Free Grammar.
11 September to 9 October 2009 Publication of statutory proposals and notices for Spen Valley Sports College, The Community Science College @ Thornhill and Westborough High School* and 4 week representation period.
*subject to cabinet approval
25 September to 6 November 2009 Publication of statutory proposals and notices for Birkdale High School,* Earlsheaton Technology College* and 6 week representation period.
*subject to cabinet approval
10 November 2009 Cabinet meet and decide proposals for Whitcliffe Mount – SBEC (VC) *, Gomersal CE (C) Middle School*, West End Middle School* and Whitechapel Middle School*
24 November 2009 Cabinet meet and decide proposals for Spen Valley Sports College, The Community Science College @ Thornhill and Westborough High School*
8 December 2009 Cabinet meet and decide proposals for Birkdale High School* and Earlsheaton Technology College*.
* subject to cabinet approval
End of December (to 1 February 2010) Publication of 2nd Competition Notice – to publish all the proposals submitted to the LA for presentation to the community (with relevant public meeting/s).

February / March 2010

Report outcome of the 2nd competition notice and decide proposals (where the LA is not the proposer or it does not have an interest in a Trust school bid). Local authority refers proposals to the schools adjudicator for a decision, if it is the proposer or has an interest in a Trust school bid.

To be determined Implement proposals - which may involve publishing a statutory notice regarding changes/closures of schools - subject to any modifications agreed by the local authority or schools adjudicator appointed by DCSF.
** These dates are revised to those published in the printed documentation.

 

Indicative timeline for other proposals
Date Activity
Summer term 2009 Conclusion of informal consultation and 6 weeks statutory consultation on revised proposals for Batley Girls’ High School – Visual Arts College and Batley Business and Enterprise College and any associated proposal for provision on the Batley Field Hill site.
Summer term 2009 Consultation on proposals for the Whitcliffe Mount Pyramid primary schools and/or cabinet approval to proceed to the publication of statutory proposals and notices with 6 week representation period as appropriate.
Autumn term 2009 6 week statutory consultation on sixth form proposals

 