Proposals to develop Heaton Avenue First and Nursery School
Next steps and indicative timescale for Heaton Avenue
Gillian Donohoe - February 2010
school.organisation@kirklees.gov.uk
The table below shows the steps and timescales involved to develop Heaton Avenue First and Nursery School into
a 1 class entry, 3-11 Community Primary School with nursery provision on the West End Middle School/South Parade
site.
[Note:All dates are subject to Cabinet approval]
Indicative timeline for statutory processes
| Date |
Consultation and statutory proposals and notices |
| January 2010 |
Seek cabinet approval for statutory processes |
| February to April 2010 |
6-week statutory consultation for proposals to enlarge and change the upper age limit of
Heaton Avenue First and Nursery School |
| April 2010 |
Report outcomes of the consultation to Cabinet and seek approval to publish proposals |
| May 2010 |
Publication of statutory proposals and notice and start of 6 week representation period |
| July 2010 |
Cabinet meet and decide proposals for Heaton Avenue |
| September 2011 onwards |
Implement proposals |
| |
|