Local Development Framework consultation timeline
Development, Planning and Information Team (dpi@kirklees.gov.uk)
Last updated - November 2011
On this page
About the timeline
The Local Development Framework (LDF) is made up of a number of documents. Each document goes through a number of stages of consultation before being formally adopted. The consultation stages for the documents which make up the LDF are shown below.
The timetable for the LDF is called the Local Development Scheme (LDS).
Statement of Community Involvement (SCI)
| Stage | Date |
|---|---|
| SCI Draft document consultation | October 2005 |
| SCI Draft document submission consultation | January 2006 |
| SCI Adoption | September 2006 |
Development Plan Documents (DPDs) including Area Action Plans
| Stage | Date |
|---|---|
| DPD1 Issues and Options consultation | October - December 2005 |
| DPD1 Preferred Options (2006) Consultation and Sustainability Appraisal (now classified as part of the Issues and Options stage) | June - July 2006 |
| DPD1 Sustainability Appraisal Scoping Report (2008) | April 2008 |
| DPD1 Options consultation (2009) and Sustainability Appraisal | February - April 2009 |
| DPD1 Draft proposals (preferred option) consultation | December 2010 |
| DPD1 publication and representations period | January 2012 |
| DPD1 Expected Adoption | January 2013 |
| Stage | Date |
|---|---|
| No stages published | No dates published |
| Stage | Date |
|---|---|
| DPD3 Issues and Options consultation - Huddersfield Area Action Plan | November 2009 |
Supplementary Planning Documents (SPDs)
| Formerly SPD10 - Developer Contributions Transport, Leeds Road, Huddersfield | |
| Stage | Date |
|---|---|
| SPD1 Preparatory documents | October - December 2005 |
| SPD1 Draft document consultation and Sustainability Appraisal | January - March 2006 |
| SPD1 Adoption | September 2007 |
| Stage | Date |
|---|---|
| SPD2 Preparatory documents | October - November 2007 |
| SPD2 Draft document consultation and Sustainability Appraisal | April - May 2008 |
| SPD2 Adoption | November 2008 |
| Stage | Date |
|---|---|
| Consultation | To be confirmed |
| Expected Adoption | To be confirmed |
Contact the Development, Planning and Information Team
- Development, Planning and Information Team
- Market Street, PO Box B93, Civic Centre 3, Huddersfield, HD1 2JR
- 01484 221627
- dpi@kirklees.gov.uk